3. Timeline
Project Start Date: Thu 4/28/05
Project Finish Date: Mon 8/15/05
| Task |
Start | Finish |
|---|---|---|
| Refine prototypes for beta test version | 5/2/05 | 5/19/05 |
| Departmental Interviews/Focus groups | 5/2/05 | 5/20/05 |
| Select prototype and refine for user testing | 5/20/05 | 7/20/05 |
| Select questions for online survey | 6/03/05 | 6/17/05 |
| Write tasks for usability testing | 6/17/05 | 7/15/05 |
| Online survey of minimum 50 individuals to create pool of usability testing participants - received 60 responses | 7/11/05 | 7/22/05 |
| Task-based usability testing - 8 indivduals selected from survey respondents - 2 undergraduate, 2 graduate, 2 staff, 2 faculty | 7/25/05 | 8/01/05 |
| Meeting to discuss test results | 8/1/05 | 8/1/05 |
| Re-design based on usability feedback | 8/1/05 | 8/13/05 - In progress |
| Develop process for updating individual pages within the library website | 8/13/05 | 8/27/05 - In progress |
| Follow-up task-based usability testing | Fall 2005 Session | |