3. Timeline

Project Start Date: Thu 4/28/05
Project Finish Date: Mon 8/15/05

Task
Start Finish
Refine prototypes for beta test version 5/2/05 5/19/05
Departmental Interviews/Focus groups 5/2/05 5/20/05
Select prototype and refine for user testing 5/20/05 7/20/05
Select questions for online survey 6/03/05 6/17/05
Write tasks for usability testing 6/17/05 7/15/05
Online survey of minimum 50 individuals to create pool of usability testing participants - received 60 responses 7/11/05 7/22/05
Task-based usability testing - 8 indivduals selected from survey respondents - 2 undergraduate, 2 graduate, 2 staff, 2 faculty 7/25/05 8/01/05
Meeting to discuss test results 8/1/05 8/1/05
Re-design based on usability feedback 8/1/05 8/13/05 -
In progress
Develop process for updating individual pages within the library website 8/13/05 8/27/05 -
In progress
Follow-up task-based usability testing Fall 2005 Session